Equipo auxiliar y sistemas integrados
e-mail [email protected] Idioma EN ES
Casos de éxito

Multi-Stage VOC Removal & Deodorization System Retrofit on a 1,200 kg/h r-HDPE Bottle Recycling Line

Industrial case study: Retrofit of a multi-stage VOC removal and deodorization system on a 1,200 kg/h post-consumer r-HDPE bottle recycling line, achieving 96.8% VOC removal efficiency.

  • Existing Line Retrofit
  • Plastic Recycling Plants
  • HDPE
  • Thermoplastic Elastomer
  • Pellets
  • Regrind
  • Blockage and bridging
  • Residual odor and VOC
Etapa verificada
In Operation
Fecha del proyecto
2024-05
Identidad del cliente
Anonymized
Ubicación del proyecto
East China Industrial Park
Placeholder image: project photo, set as the featured image, 1600 × 900 px (16:9). It shows the space reserved for approved material and is not a photograph of our equipment.
Placeholder · 1600 × 900 px (16:9)(占位图) Replace with an approved project photo, set as the featured image at this size.(按此尺寸替换为正式图片。)

The situation

Where this project started

A project is read from the conditions it began with — the profile, the background and the constraints are the customer's, and the result only means something beside them.

Objetivo del cliente

Capture and treat 100% of fugitive emissions from extruder degassing ports and the pelletizer shroud; achieve Non-Methane Hydrocarbon (NMHC) emissions < 20 mg/m³ at the exhaust stack, and reduce workshop odor concentration to ≤ 30 OU (Odor Units) without causing backpressure on the extruder vacuum pumps.

Perfil del cliente

An established post-consumer plastic recycling enterprise in East China operating three multi-stage extrusion pelletizing lines with a combined annual capacity of 25,000 tons of high-grade recycled HDPE (r-HDPE) granules for industrial containers and drainage pipes.

Antecedentes del proyecto

Post-consumer HDPE bottle flakes frequently carry stubborn residues of laundry detergents, cooking oils, fragrance surfactants, and printing inks. When melted at 200°C–230°C in an extruder barrel, these contaminants undergo severe thermal desorption and partial cracking, releasing volatile short-chain hydrocarbons, acrolein, fatty acids, and noxious organic odors that violate environmental discharge standards.

Condiciones iniciales

The existing 1,200 kg/h r-HDPE single-screw recycling line operated with an open water ring pelletizer and two vacuum degassing ports venting directly into the workshop atmosphere. Workshop ambient VOC concentration exceeded 85 mg/m³, with dense oil mist accumulation on roof steel structures and recurring complaints from surrounding industrial park facilities.

Limitaciones clave

The system had to be retrofitted without altering the existing extruder’s vacuum degassing efficiency (-0.095 MPa), and outdoor installation footprint was restricted to an 8.5 m x 3.5 m equipment corridor beside the plant perimeter wall.

Delivery

What was delivered, and why it was chosen

The scope below is what this project actually received; the configuration snapshot is the one agreed for this delivery, not a current product sheet.

Por qué esta selección

A multi-stage mechanical demisting + electrostatic precipitation (ESP) + deep-bed carbon system was chosen over direct thermal oxidation (RTO) because the exhaust volume (15,000 m³/h) carried significant sub-micron oil droplets that would clog RTO ceramic media, while carbon adsorption provides low operational energy cost and rapid ROI for intermittent recycling loads.

Personalización específica del proyecto

Custom SUS304 capture hoods were designed with gas-tight silicone seals contoured exactly to the extruder vacuum ports and pelletizer chute, equipped with counterweighted manual balance dampers to prevent air infiltration from overloading the system.

Alcance entregado

  • System Plastic VOC Removal & Deodorization System VOC-15000: Multi-stage unit with demister, dual-field ESP, 6.0 m³ carbon bed, and 15 kW ex-proof fan

    Main industrial exhaust abatement skid treating all vacuum vent and pelletizing exhaust streams.

    Fully skidded unit mounted outdoors adjacent to extrusion bay, wired to master PLC.

    1 set
  • Equipment Negative-Pressure Capture Hoods & Stainless Ducting SUS304 custom enclosure hoods with pneumatic blast dampers and quick-release inspection doors

    Captures 98%+ of fugitive vapors directly at the twin degassing vents and water-ring cutting hood.

    Included 45 meters of SUS304 ductwork with condensate drain traps.

    1 set
  • Equipment High-Efficiency Plate Electrostatic Precipitator (ESP) Dual-stage high-voltage ionizer-collector cells, rated air volume 15,000 m³/h, 72 kV peak voltage

    Ionizes and collects sub-micron oily aerosols and plasticizer droplets to prevent carbon bed fouling.

    Automatic spark quench and high-voltage power regulation cabinet included.

    1 set
  • Service On-Site Integration, Balancing & Commissioning Service Field engineering team on-site for 5 days including third-party emission certification testing

    Air balance calibration, electrical hookup, and emission compliance sign-off.

    Included operator maintenance training for ESP plate cleaning and carbon replacement.

    1 service

Verification

How far the project is verified

A stage is written down only when there is evidence for it; a project that is running says so, and a project still in the factory does not claim more.

  1. Factory Tested

    The complete VOC treatment skid underwent factory dry-run testing before dispatch: fan dynamic balance verification, ESP high-voltage dielectric breakdown test at 75 kV, and air tightness pressure testing on the carbon vessel housing.

  2. Shipped

    The treatment skid and pre-fabricated stainless ducting were transported via two 13.5-meter flatbed logistics trucks with all components weather-wrapped and crated.

  3. Installed

    The outdoor skid was positioned on a concrete pad adjacent to the plant wall. Stainless steel ducting was routed through high-level penetrations down to the extruder ports over a scheduled 36-hour planned maintenance shutdown, causing zero unplanned production downtime.

  4. Commissioned

    The system was commissioned over three consecutive 8-hour production shifts with the customer’s r-HDPE recycling line running at full 1,200 kg/h capacity. Gas sampling probes measured inlet and outlet NMHC concentrations, ESP current stability, and air pressure drop across the activated carbon bed.

  5. In Operation Verified

    The system has operated continuously for over 14 months on a 24/7 basis. Routine maintenance consists of monthly ESP collector plate high-pressure hot water washing and annual activated carbon replacement.

Results

What changed, and what backs it

Every result names its evidence. A number without the method and conditions behind it would not be a result worth quoting.

Stack NMHC Emission Concentration

580 18.5

mg/m³

Stack Non-Methane Hydrocarbon (NMHC) emissions dropped from 580 mg/m³ to 18.5 mg/m³, achieving 96.8% VOC removal efficiency and easily satisfying local environmental standards (< 50 mg/m³).

Evidencia Customer Confirmation

Duración de la prueba
24-hour continuous monitoring
Fecha de la evidencia
2024-05
Condiciones reales de entrada y salida
Extrusion of washed r-HDPE milk jugs and detergent bottle flakes at 1,200 kg/h, melt temperature 215°C.
Método de medición
Gas chromatography-flame ionization detection (GC-FID) according to HJ 38-2017.

Exhaust Odor Concentration (Dilution-to-Threshold)

1500 30

OU (dimensionless)

Exhaust odor concentration was reduced from over 1,500 OU to ≤ 30 OU, completely eliminating acrid plastic fumes and pungent perfume odors from surrounding industrial receptors.

Evidencia Commissioning Record

Duración de la prueba
Triplicate shift sampling
Fecha de la evidencia
2024-05
Condiciones reales de entrada y salida
Continuous operation during daytime and night shifts across the extrusion hall.
Método de medición
Dynamic olfactometry triangle bag method according to GB/T 14675.

Zero Unplanned Shutdowns

The integrated negative-pressure draft control prevented any oily mist buildup inside the extruder vacuum lines, maintaining steady vacuum degassing without a single emission-related plant shutdown in over a year.

Evidencia Customer Confirmation

Duración de la prueba
12 months continuous operation
Fecha de la evidencia
2024-11
Condiciones reales de entrada y salida
Ongoing 24/7 production over 12 months.
Método de medición
Maintenance log inspection.

Evidence

Pictures, videos and records

Only material the customer has cleared for publication is shown here.

  • Placeholder image: photo of the installed section at the plant, 1200 × 900 px (4:3). It shows the space reserved for approved material and is not a photograph of our equipment.
    Placeholder · 1200 × 900 px (4:3)(占位图) Replace with an approved photo of the installed section at the plant at this size.(按此尺寸替换为正式图片。)
  • Placeholder image: photo from the factory test or the installation, 1200 × 900 px (4:3). It shows the space reserved for approved material and is not a photograph of our equipment.
    Placeholder · 1200 × 900 px (4:3)(占位图) Replace with an approved photo from the factory test or the installation at this size.(按此尺寸替换为正式图片。)
Siguiente paso

Solicitar cotización

Indíquenos el material, el proceso y el resultado que necesita lograr. Los detalles técnicos se pueden completar más adelante junto con nuestro equipo de ventas.

Solicitar cotización
Solicitar cotización