Equipo auxiliar y sistemas integrados
e-mail [email protected] Idioma EN ES
Casos de éxito

2,000 kg/h Vibrating Spiral Elevator Vertical Cooling & Classification Replacement for a PP Pelletizing Facility

Industrial case study: 2,000 kg/h Vibrating Spiral Elevator cooling and classification replacement on a PP extrusion pelletizing line, cooling pellets from 88°C to ≤ 38°C.

  • Equipment Replacement
  • Plastic Extrusion Pelletizing Plants
  • PE(Polyethylene)
  • PP(Polypropylene)
  • Pellets
  • Insufficient cooling
  • Off-spec pellet size and fines
  • Sticking and agglomeration
Etapa verificada
In Operation
Fecha del proyecto
2024-04
Identidad del cliente
Anonymized
Ubicación del proyecto
East China Petrochemical Park
Placeholder image: project photo, set as the featured image, 1600 × 900 px (16:9). It shows the space reserved for approved material and is not a photograph of our equipment.
Placeholder · 1600 × 900 px (16:9)(占位图) Replace with an approved project photo, set as the featured image at this size.(按此尺寸替换为正式图片。)

The situation

Where this project started

A project is read from the conditions it began with — the profile, the background and the constraints are the customer's, and the result only means something beside them.

Objetivo del cliente

Cool 2,000 kg/h of hot PP pellets from 85°C–90°C down to ≤ 40°C prior to packaging, eliminate pellet caking in 1,000 kg bulk bags, reduce fines (< 1.5 mm) below 0.05%, and reclaim over 20 meters of workshop floor space.

Perfil del cliente

A major polyolefin extrusion pelletizing enterprise in East China operating six continuous single- and twin-screw extrusion lines with an annual pelletizing volume exceeding 60,000 tons of virgin and compounded PP/PE resins.

Antecedentes del proyecto

Polyolefin resins (PP/PE) exhibit semi-crystalline solidification behavior. If pellets are packaged before core temperature drops below 40°C–45°C, residual latent heat induces post-crystallization creep, fusing pellets into stubborn lumps inside bulk shipping containers and destroying customer process automation.

Condiciones iniciales

The client operated an open 24-meter horizontal vibrating cooling bed. Hot PP pellets (88°C) arrived at the bagging station at over 65°C, softening and fusing under compressive stack pressure inside 1-ton bulk bags. In hot summer weather, relative humidity exceeded 80%, causing pellet moisture re-absorption and generating mold flash complaints.

Limitaciones clave

Total allocated floor footprint could not exceed 2.0 m x 2.0 m, while elevating material 5.5 meters to reach the overhead bagging surge bin.

Delivery

What was delivered, and why it was chosen

The scope below is what this project actually received; the configuration snapshot is the one agreed for this delivery, not a current product sheet.

Por qué esta selección

A Vibrating Spiral Elevator was selected over pneumatic cooling dilute-phase systems or long water flumes because it combines 5.5-meter vertical elevation with 120 seconds of gentle, non-degrading air cooling within a Ø1.4 m footprint, consuming 75% less electrical power than pneumatic conveying blowers.

Personalización específica del proyecto

Equipped with dual counter-rotating vibratory motors with adjustable eccentric weights and heavy-duty polyurethane elastomeric isolators, achieving 97.5% vibration absorption to prevent dynamic resonance transmission to the mezzanine structure.

Alcance entregado

  • Equipment Vibrating Spiral Elevator Cooling Tower VSE-1455: Tower diameter 1,400 mm, lift height 5.5 m, SUS304 spiral flighting, dual 3.7 kW vibratory motors, 2,000 kg/h capacity

    Lifts pellets vertically while providing 120 seconds of convective air cooling over a 48-meter developed spiral path.

    Configured with air-knife plenum covers and reinforced base dampening springs.

    1 set
  • Equipment Linear Vibrating Screen Classifier LVS-1225: Dual-deck linear vibrating screen (4.5 mm top deck, 1.8 mm bottom deck), SUS304 mesh, quick-release clamps

    Scalps agglomerates and removes micro-dust fines directly beneath the spiral elevator discharge.

    Equipped with dust aspiration hood.

    1 set
  • System Refrigerated Air Dehumidification & Chiller Skid AC-20HP: Closed-loop industrial air chiller supplying 15°C dehumidified cooling air at 4,500 m³/h

    Blows high-velocity chilled dry air across spiral flights to accelerate conductive and convective cooling.

    Equipped with washable G4 pre-filter and F8 secondary air filter.

    1 set
  • Service Turnkey Demolition, Rigging & Commissioning Service Complete removal of legacy horizontal conveyors, rigging, electrical integration, and thermal imaging sign-off

    Full turnkey installation executed in 4 days during plant annual maintenance turnaround.

    Included 12-month preventive vibration monitoring checkups.

    1 service

Verification

How far the project is verified

A stage is written down only when there is evidence for it; a project that is running says so, and a project still in the factory does not claim more.

  1. Factory Tested

    Resonant vibration frequency and amplitude mapped at 1.8 mm stroke; motor phase synchronization verified; all SUS304 spiral welds dye-penetrant tested to ensure zero micro-cracks under cyclic vibratory loading.

  2. Shipped

    Shipped in two open-top transport cradles with vibratory drive motors secured with transport locking brackets.

  3. Installed

    Installed over a 4-day scheduled annual maintenance shutdown. Legacy horizontal cooling conveyor dismantled; new spiral elevator anchored to heavy inertia foundation pad; ductwork connected to chiller skid.

  4. Commissioned

    Commissioned over 48 hours of uninterrupted extrusion of homopolymer PP (MFI 3.0 g/10 min) at 2,050 kg/h throughput. Thermal imaging cameras recorded continuous pellet temperatures along each tier of the 5.5-meter spiral tower, and inline sieving tests confirmed zero blinding on the dedusting screen.

  5. In Operation Verified

    In continuous operation for over 15 months on a 24/7/365 production schedule, handling over 22,000 tons of polyolefin pellets with zero vibration spring fatigue failures or downtime.

Results

What changed, and what backs it

Every result names its evidence. A number without the method and conditions behind it would not be a result worth quoting.

Final Pellet Packaging Core Temperature

66.8 37.5

°C

Final pellet packaging temperature was reduced from 66.8°C down to 37.5°C under continuous 2,050 kg/h throughput, completely eliminating post-packaging pellet fusion and bulk bag caking.

Evidencia Commissioning Record

Duración de la prueba
48 hours continuous extrusion trial
Fecha de la evidencia
2024-04
Condiciones reales de entrada y salida
Continuous thermocouple and calibrated FLIR thermal camera monitoring at pellet discharge.
Método de medición
Contact digital insertion thermometer and FLIR calibrated thermal imaging at spiral discharge.

Pellet Fines & Dust Content (< 1.5 mm)

0.18 0.015

%

Pellet fines and dust content entering bulk packaging dropped from 0.18% to 0.015%, meeting high-end optical film and medical molding virgin resin cleanliness specifications.

Evidencia Factory Test Record

Duración de la prueba
5 production lots (100 tons total)
Fecha de la evidencia
2024-04
Condiciones reales de entrada y salida
Sieve analysis of 50 kg pellet composite sample according to ASTM D1921.
Método de medición
Mechanical sieve shaker analysis (passing 1.5 mm screen).

Floor Footprint Occupied by Cooling Equipment

28.5 3.2

m²

Floor footprint occupied by the cooling system shrank from 28.5 m² to 3.2 m², liberating over 25 m² of prime factory floor space for forklift maneuvering and warehousing.

Evidencia Internal Project Record

Duración de la prueba
Immediate upon installation
Fecha de la evidencia
2024-04
Condiciones reales de entrada y salida
Floor footprint measurement before and after equipment replacement.
Método de medición
Surveyed equipment floor footprint area (m²).

Evidence

Pictures, videos and records

Only material the customer has cleared for publication is shown here.

  • Placeholder image: photo of the installed section at the plant, 1200 × 900 px (4:3). It shows the space reserved for approved material and is not a photograph of our equipment.
    Placeholder · 1200 × 900 px (4:3)(占位图) Replace with an approved photo of the installed section at the plant at this size.(按此尺寸替换为正式图片。)
  • Placeholder image: photo from the factory test or the installation, 1200 × 900 px (4:3). It shows the space reserved for approved material and is not a photograph of our equipment.
    Placeholder · 1200 × 900 px (4:3)(占位图) Replace with an approved photo from the factory test or the installation at this size.(按此尺寸替换为正式图片。)
Siguiente paso

Solicitar cotización

Indíquenos el material, el proceso y el resultado que necesita lograr. Los detalles técnicos se pueden completar más adelante junto con nuestro equipo de ventas.

Solicitar cotización
Solicitar cotización